| BETWEEN: | Mr. Lumb | | APPELLANT |
| AND: | Environmental Health Officer | RESPONDENT | |
| BEFORE: | D. Brown | Chair |
| DATE OF HEARING: | June 8, 1995 | ||
| PLACE OF HEARING: | Richmond, BC |
| APPEARING: | For Appellant | |
| Spokesperson: | John Enevoldson, P. Eng. | |
| Witness: | Peter Peart | |
| For Respondent | ||
| Spokesperson: | Tim Adams | |
| Witnesses: | Tom Weston | |
| Bill Purtell |
This was an appeal against the December 19, 1994, denial of a
Sewage Disposal System for Lot 3, Block 6, DL 1397, Plan 4479
- Garden Bay.
APPEAL
The authority for the Panel of the Environmental Appeal Board
to hear this appeal is found in the Health Act, s.5(3)(a),
and in the Environment Management Act, s.11.
BACKGROUND
This appeal concerns the rejection of an application for the installation
of an on-site Sewage Disposal System on a property [the "Site"]
located in the Garden Bay area of Pender Harbour.
The Site is legally described as Lot 3, Block 6, District Lot
1397, Plan 4474. It is approximately 1/4
acre in size and is ocean waterfront. At the present time the
applicant also owns the adjoining Lot 2; Lot 3 appears to have
had for some time common ownership with the adjoining Lot 2 and
has presumably in the past been treated by the owner of Lot 2
as part of the grounds for that property.
The Appellant advised that he wants to develop Lot 3 so that he
can pass on this property and Lot 2 to his children. The owner's
plans for the properties are however irrelevant to this appeal.
The Appellant applied for a permit to install an on-site Sewage
Disposal System designed by John Enevoldson, a professional engineer.
The application for the permit was refused by the Respondent.
The primary reasons for the refusal are set out in a letter dated
May 23,1995, from Timothy H. Adams, Environmental Health Officer.
At the hearing evidence was given by the Appellant and by two
professional engineers, namely, John Enevoldson and Peter Peart
on behalf of the Appellant and by Timothy Adams, Tom Weston and
Bill Purtell on behalf of the Respondent. Mr. Greg Carriere,
Regional Public Health Engineer, was not called as a witness for
the Respondent although a report (Memorandum) from Mr. Carriere
was included in the material. The Appellant did not have the
opportunity to cross-examine Mr. Carriere with respect to the
contents of this report.
Mr. John Enevoldson is a civil engineer with recent experience
in the design of on-site Sewage Disposal Systems and Peter Peart
is a Geotechnical engineer with many years of experience in his
area of expertise with impressive professional credentials. Both
witnesses were qualified to give expert opinion evidence.
The proposed on-site Sewage Disposal System was designed by John
Enevoldson. It consists of the following components:
In the remainder of this decision this disposal system will for
purposes of brevity be referred to as the Enevoldson Proposal.
There are two abandoned driveways on the Site. These driveways
have at one time provided access to adjoining lots - they do not
appear to have ever been subject to major vehicular traffic.
The Site is extensively landscaped with a number of mature trees.
Peter Peart referred to it as a Stanley Park.
LEGAL CONTEXT
This appeal is taken pursuant to section 5 of the Health Act.
The Environmental Appeal Board may confirm, vary or rescind the
ruling under appeal.
The relevant regulation is BC Reg. 411/85 "Sewage Disposal
Regulation", a regulation passed pursuant to section 5 of
the Health Act.
Section 6 of BC Reg. 411/85 regulation provides as follows:
Subsection 7(1) provides that "where a medical health officer
... is satisfied that it is impossible for a person to comply
with ... (b) in the case of a conventional package treatment
plant system. sections 11, 12, or 18 of Schedule 3, but that the
person can comply with all other provisions of the appropriate
schedule, he may issue a permit to construct under section 3,
containing conditions that he considers appropriate to meet the
omitted standards having regard to safeguarding public health."
Ministry of Health Policy 6.1 states "To accommodate an owner
of an existing lot, an alternate system shall be considered."
Although this is a policy and hence does not have the force of
the Act or the regulations it is in the spirit of the law; namely,
that an owner of an existing lot will be accommodated in the development
of the lot provided that this development does not constitute
a risk to public health as stated in the regulations.
REVIEW OF THE DECISION OF THE RESPONDENT
The Timothy Adam's May 23, 1995, letter sets out the following
major concerns with the Enevoldson Proposal:
Peter Peart's evidence is that there is approximately 1.5 metres
(5 feet) depth of permeable soil over the relevant area. This
permeable soil is a mixture of organic and inorganic material
(largely gravely sand and sandy gravel) and meets all percolation
requirements with a percolation rate of 2.5 minute per inch.
Glacial till underlies the surface soil; this glacial till is
largely impermeable, The evidence is that the 1.5 meters (5 feet)
of permeable soil has very good (effluent) treatment qualities.
Based on the whole of the evidence but in particular on the expert
evidence of Peter Peart the Panel finds that the groundwater table
is coincident with the upper layer of the glacial till. The upper
level of the glacial till is approximately 1.5 to 2 meters (5
feet to 6.5 feet) below the surface. This finding with respect
to the groundwater table is supported by the test holes with the
possible exception of one hole. No water was observed in the
two deepest test holes (respectively 7-1/2
and 8-1/2 feet deep[25 to 28 metres]) in the
middle of the rainy season. The permeable soil is in an unsaturated
condition in the winter.
Peter Peart gave expert evidence concerning the issue of the degree
of modification of the soil structure in the old driveway due
to compaction. His evidence was that there had not been significant
compaction but that in any event the soil could easily be restored
to its natural condition.
The evidence established that the driveway area had not been measurably
compacted but to the extent that any compaction had occurred this
would be remedied by the Enevoldson Proposal. Existing excavations
in other parts of the site are insignificant - in any event the
Panel is not convinced that there is less than 1.2 meters (4 feet)
of native, porous soil at such sites.
I find that the proposed on-site waste disposal system does not
include a built up absorption field such as is defined in the
policy statement. A Built Up Absorption Field is defined as follows:
This describes a field which is an area of land uniformly raised
above the natural ground level. The Enevoldson proposal
contemplates returning the relevant area to its natural contours
in some parts and some contouring in other parts to reduce the
slope to 30%.
This definition describes something more than the minor alterations
proposed by the Appellant which included some contouring to return
the field to its natural slope at several locations.
Accordingly the Panel finds that the required length for the absorption
field are those set out in Schedule 3 which are the package treatment
plant absorption field lengths and that the Enevoldson Proposal
exceeds these requirements substantially.
The runs in the absorption field are required to be three meters
apart if the slope is in excess of 30 percent. John Enevoldson
noted that the spacing between the trenches for runs 1 & 3
(primary field) are 14 feet (4.3 meters) and between runs 2 &
4 (reserve field) are 17 feet (5.2 metres). The Panel finds that
this manner of interpreting the spacing requirements as set out
in the regulations is appropriate in the circumstances and that
the operational runs are more than 3 meters (9.8 metres) apart.
Various estimates were given as to the ground slope of the disposal
field; however, the current slope is at least 35%. The Enevoldson
Proposal proposes a reduction to 30% by adding approximately 6
inches of fill at the upper edge of the existing rock wall. The
regulations do not prohibit an engineered reduction of a slope.
Accordingly for the purposes of this appeal and the consideration
of the Enevoldson Proposal the slope should be considered to be
30%. In any event section 7 of BC Regulation 411/85 allows for
exceptions to the slope requirement having "regard to safeguarding
public health".
Ministry of Health Policy - On-Site Sewage Disposal Chapter 4.4
says "As a condition of permit pursuant to section 3(5) in
order to prevent domestic sewage from reaching the surface of
the ground, the setback distance from a sewage disposal system
and potential downslope breakout points, such as present or future
roadcuts, excavations, an exposed impervious layer in a ditch
or a curtain drain, under normal conditions should generally not
be less than 15.25 meters (50 feet)".
The Respondent contended that the terraced cuts in the surface
of the Site, the abandoned driveway, excavations for foundation
walls and even the property line should be considered as potential
breakout points. The property line was included as a potential
breakout point on the basis that a future owner of the adjoining
lot could excavate along his property line.
What constitutes a breakout point? This is a matter which is
possibly not treated consistently; for example, in the instant
case the Respondent appears to suggest that any cut into the top
four feet of permeable soil constitutes a break out point or potential
break out point whereas it might be argued that to constitute
a breakout point or a potential breakout point the cut must reach
through to the underlying impermeable alluvial fill. The latter
interpretation may be based on the assumption that once the water
leaves the pressure distribution system it filters down to the
top of the impermeable layer and then travels along the top of
the impermeable layer.
Based on Peter Peart's testimony there is absolutely no reason
to believe that the domestic sewage in the instant case will reach
the surface of the land or discharge into a surface body of fresh
water [per section 2(2)] of BC Regulation 411/85.
In any event - even if the Respondent's understanding of an existing
breakout point was largely accepted (which the Panel does not)
- the Panel finds that the Enevoldson Proposal eliminates any
potential breakout points within fifty feet of the disposal field.
The only existing areas on Lot 3 which both parties acknowledged
might arguably be potential breakout points on Lot 3 are a rock
wall constructed on the site by a previous owner and perhaps the
Roadway. The Enevoldson Proposal eliminates both the rock wall
and the roadway as potential breakout points. The regulations
do not prohibit an engineered elimination of breakout points or
potential breakout points. It should be emphasized that the Panel
has not made a finding that either the rock wall or the Roadway
are actual breakout points.
Furthermore the Panel does not accept the contention of the Respondent
that the boundary of the property can be considered a potential
breakout point. It is a somewhat unlikely scenario that a future
owner of Lot 2 would excavate along the boundary between the properties.
Surely a potential breakout point is not so large a concept as
to encompass any future event however, unlikely. In any event
the owner of Lot 3 could probably enjoin a future owner of Lot
2 (or Lot 4) from removing lateral support for (the ground of)
Lot 3.
John Enevoldson's evidence, which is accepted, is that no actual
breakout points have been observed by anyone in the recent past.
Peter Peart was not able to identify any actual breakout points
including in the beach area. He found no indicia of a breakout
point in the beach area. Based on the evidence, including Mr.
Peart's, that once the largely purified water leaves the secondary
treatment plant and has travelled through the field, anything
left would percolate through the 48 or more inches of permeable
soil and probably end up in a fracture in the substratum.
DECISION
The Enevoldson Proposal is a well thought out Sewage Disposal
System with a number of built-in safeguards. Despite the moderately
steep terrain and the relatively small area of the Lot the Panel
believes that with the proper implementation of this system there
is little likelihood of effluent from this particular Lot reaching
Hospital Bay or otherwise endangering public health.
In conclusion the Panel finds that the Enevoldson Proposal complies
with the Health Act and regulations passed there under.
Accordingly, the appeal is allowed.
More particularly the Panel finds that the Enevoldson Proposal
substantially complies with Schedule 3 (including sections 11,
12, and 18); however, if any parts of the Enevoldson Proposal
do not comply with sections 11, 12, and 18 the Panel finds that
a permit can be issued such that with the impositions of the conditions
as hereinafter outlined, the public health can be safeguarded
as contemplated by the Act and regulations.
CONDITIONS
The following conditions will apply:
i. A secondary treatment plant
ii. A storage tank
iii. A 600 imperial gallon pump chamber
iv. An absorption field utilizing a pressure system
v A safety trench
vi. Treatment of the earth, filing and contouring at various
points
b) The Appellant must use an approved secondary treatment plant
- according to the evidence there are only two approved systems
at the present time. The Ministry may choose either of these
systems. Mr. Peart recommended a Biocycle 5800 Package Treatment
Plant - his evidence was that the effluent once treated by this
system is practically drinkable. The Ministry however advised
that this system is not yet approved. Alternatively the Respondent
may choose this system if approval can be obtained for it.
c) Both Mr. Enevoldson and Mr. Peart gave evidence that there
is excellent vegetation on the Site. This vegetation was advanced
as an integral and important part of this proposal. Mr. Enevoldson
indicated that the Appellant was prepared to have the trenches
in the absorption field for the pressure distribution system dug
in order to protect the vegetation. Given the importance of preserving
the vegetation and the slope of the terrain, the Ministry of Health
may require that all trench work be dug so that there is minimal
disturbance of the vegetation.
d) Before the permit is issued the easement registered over
Lot 3 (location of driveway) must be cancelled and a State of
Title Certificate confirming such must be provided to the Environmental
Health Officer.
e) Additionally the Minister of Health may require that a covenant
pursuant to section 215 of the Land Title Act be registered
against the Property. This covenant would require that the septic
system be installed and maintained as set out in the Enevoldson
Proposal.
ii. That date one month after the date that the driveway easement has been discharged from the Title and the section 215 covenant -if required by the Respondent - has been registered against the Title.
h) All earth treatment including scarifying, contouring, back filling, etc.,, referred to in the Enevoldson Proposal must be completed to acceptable standards using approved materials.
i) The Respondent may require reasonable modifications to the specifications for the pressure distribution system.
j) The Environmental Health Officer may specify reasonable inspection requirements during the course of installing the System.
k) The Sewage Disposal System should be certified installed
in accordance with the Enevoldson Proposal (as herein modified)
by a professional engineer (which may be Mr. Enevoldson).
j) Any of the above, where appropriate, can be included in the conditions attached to the permit to be issued by the Respondent. The Respondent can also include reasonable periodic inspection and maintenance requirements for the System.
David Brown, Panel Chair
Environmental Appeal Board
August 17 , 1995